Drona 2016 is IIM Indore’s unique mentorship program designed for candidates to get a sneak-peak into the lives of management students and to develop an understanding about this career option. It consists of interactions with IIM I professors and renowned industrialists during the program, coupled with challenging activities designed to test skills like leadership, team building, strategising etc. It also provides an insight into the 2 year course and career avenues thereafter.For more details visit - facebook.com/drona.iris


A train running at the speed of 60 km/hr crosses a pole in 9 seconds. What is the length of the train?

A train running at the speed of 60 km/hr crosses a pole in 9 seconds. What is the length of the train?

A team of 80 men is supposed to do a work in 64 days. After 36 days, 20 more men were employed and the work finished 2 days earlier. How many days would it have been delayed if 20 more men were not employed?

A team of 80 men is supposed to do a work in 64 days. After 36 days, 20 more men were employed and the work finished 2 days earlier. How many days would it have been delayed if 20 more men were not employed?

A team of 80 men is supposed to do a work in 64 days. After 36 days, 20 more men were employed and the work finished 2 days earlier. How many days would it have been delayed if 20 more men were not employed?


three man A,B,C working together can do a job in 6 hrs less time than A alone, in 1 hr less time than B alone and in half the time needed by C when working alone. Then A and B together can do the job in

Six small pumps and three large pumps are fitted to a tank. Each small pumps works 2/3rd the rate of each large pump. If all the pumps work together what fraction of the time taken by a single large pump, will they take to fill the tank?



I have been doing Time and Work. There, I am finding calculations involving fractions. How can I easily solve them ?
For example, how will you calculate 3.33/8.33?

3 men and 4 boys can earn rs 765 in 7 days. 11 men and 13 boys can earn rs 3008 in 8 days. in what time will 7 men and 9 boys earn rs 2480?



????
total number of man days = 80*64= 5120.
From given condition total number of man days = (36*46+26*100)= 5480 man days
additional number of man days = (5480-5120) = 360
so M*D= 360
80*d= 360
D = 4.5.