@skumar1674 @skumar1674  ·  11 Jan, 2017

WORK DONE BY A IN 10 DAYS=10/(200/3)=3/20 th Part of work

  • reply
  • favorite_border 
Santanu Kundu  @santanu2012  ·  12 Jan, 2017

Work done by A in 10 days =(75/5)= 15%. Total work done by A in 60 days= (75+15)=90%. Work done by B =(100-90)=10%. 100% work done by B in =(10/10)*100= 100 days...